Manufacturing Facility of HOME RICHARD & SONS CZ s.r.o., Červený Kostelec - 1st Stage
Investor HOME RICHARD & SONS CZ s.r.o.
The subject matter of the project documentation was the construction of a manufacturing facility for & HOME RICHARD SONS CZ s.r.o. in the town of Červený Kostelec. As the first stage, a single-storey hall (70x46 m) with a height of  9 m to manufacture and process PE films was designed. A two-storey administrative building with sanitary facilities for the employees is located in the north part of the building plot. The investment also included a fence, roads and parking areas on the premises including an access road connected to the III/3036 road as well as the underground utilities. The load-bearing structure of the hall consists of a prefabricated reinforced concrete frame with an offset envelope made from light-weight concrete panels.
Budget € 2.068 mio, w/o VAT
Build-up Area 3,200 sqm
Location of Construction Červený Kostelec
Position on the Map map
General Project Architect ORGATEX-NÁCHOD s.r.o.
Project Stage DUR / DSP / DPS
Construction Coordinator ORGATEX-NÁCHOD s.r.o.
Realization Period 2003 - 2004
ID 4248
4248-REFERENCE-INDUSTRIAL-DEVELOPMENT-HOME-RICHARD-I-STAGE

During Realization

P-4248-Realization
Installation of building envelope made from light-weight concrete panelsFinished building envelope made from light-weight concrete panelsBricked two-storey in-built sectionLaying of horizontal waterproofing material for the floor in the hallLaying of horizontal waterproofing material for hall floor
Finished floor in the hall - industrial fibre-reinforced concrete covered with PANBEX F2Work on offset parts of the two-storey in-built section with main entranceInspection DayFinished roofOverall view of hall, finishing paint job of the envelope and paved areas

Completed

P-4248-Completed
Overall view of north facade with the main entrance into the two-storey administrative in-built sectionOverall view of north facade with the main entrance into the two-storey administrative in-built sectionOverall view of north facade with the main entrance into the two-storey administrative in-built sectionNorth facade with the main entrance into the two-storey administrative in-built sectionOverall NE view
West side with entrance gates and doors into manufacturing hallOverall SE view. A bricked HVAC muffling chamber is located on the southern side of the hallOverall SE view.West facade is situated alongside road III/3036
By using this site you consent to the storage of cookies, which are necessary for the good functioning of the site.